S/N | BUDGET CODE | PROJECTS | TOTAL COST | NAME OF CONTRACTOR | 2016 APPROPRIATION |
|
1 | NREA0101121200 | RURAL ELECTRIFICATION PROJECTS IN DAURA LGA, KATSINA STATE | 416,902,518.88 | GAYACO GROUP LTD |
|
|
2 | NREA0101121008 | ELCTRIFICATION AND SUPPLY OF RELIEF TRANSFORMERS TO KADUNA NORTH LGA, KADUNA STATE |
161,407,970.50 | HAMALI TAJU NIG. LTD. |
|
|
3 | NREA0101021019 | PROVISION OF 150KW SOLAR MINI-GRID ELECTRIFICATION OF DODAN KARJI IN KAURA LGA OF KADUNA STATE | 33,073,172.00 | FANNY FRANK GLOBAL RESOURCES LTD. |
|
|
4 | NREA0101021477 | ELECTRIFICATION OF UNGUWAR GALADIMA KARJI TOWN IN CHIKUN LOCAL GOVT, KADUNA STATE |
A. J ELEC. NIG. LTD |
|
||
5 | NREA0101021019 | PROVISION OF 150KW SOLAR MINI-GRID ELECTRIFICATION OF DODAN KARJI IN KAURA LGA OF KADUNA STATE | 33,073,172.00 | FANNY FRANK GLOBAL RESOURCES LTD. |
|
|
6 | NREA0101020954 | REHABILITATION OF EXISTING /COMPLETION OF RURAL ELECTRIFICATION SCHEME IN 9 COMMUNITIES IN KADUNA STATE |
Refer to status of ongoing |
|
||
7 | Zonal Intervention | ELECTRIFICATION AND SUPPLY OF 300 KVA TRANSFORMER AT KABURDA, KAKAU WARD, CHIKUN LGA, KADUNA STATE | 9,755,770.28 | GAYACO GROUP LIMITED | ||
8 | Zonal Intervention | ELECTRIFICATION AND SUPPLY OF 300 KVA TRANSFORMER AT ANGUWAN SARKI, KAKAU WARD, CHIKUN LGA, KADUNA STATE | 9,304,871.95 | ELM ENGINEERING SERVICES LTD | ||
9 | Zonal Intervention | SUPPLY OF 4 500KVA TRANSFORMER AT ANGWAN GIMBIYA, ANGWAN PAMA, ANGWAN BARO, SAUNIN KURA, SABON TASHA WARD, CHIKUN LGA, KADUNA STATE | 10,073,540.00 | RASOLAK SERVICES (NIG.) LTD. | ||
10 | Zonal Intervention | SUPPLY OF TRANSFORMERS ZANGO KATAF/JABA FED. CONSTITUENCY,KADUNA STATE | 15,337,165.92 | MURENCO NIGERIA LTD. | ||
11 | Zonal Intervention | SUPPLY OF 500KVA TRANSFORMER AT KARATUDU, KAKAU WARD, CHIKUN LGA, KADUNA STATE | ||||
12 | Zonal Intervention | SUPPLY OF 500KVA TRANSFORMER AT NASSARAWA TOWN, NASSARAWA WARD, CHIKUN LGA, KADUNA STATE | ||||
13 | Zonal Intervention | SUPPLY OF 500KVA TRANSFORMER AT KUDENDAN, NASSARAWA WARD, CHIKUN LGA, KADUNA STATE | ||||
14 | Zonal Intervention | SUPPLY OF 500KVA TRANSFORMER AT KONAR KAJURU, KUJAMA WARD, CHIKUN LGA, KADUNA STATE | ||||
15 | Zonal Intervention | SUPPLY OF 2 500KVA TRANSFORMER AT NARAYI WARD, CHIKUN LGA, KADUNA STATE | ||||
16 | Zonal Intervention | SUPPLY OF 500KVA TRANSFORMER AT KURIGA WARD, CHIKUN LGA, KADUNA STATE |
S/N | BUDGET CODE | PROJECTS | TOTAL COST | NAME OF CONTRACTOR | PROJECT COMMENCEMENT DATE | |
1 | NREA0101121201 | PROVISION OF 500KVA AND 300KVA TRANSFORMER IN KANO STATE | 201,356,750.89 | OPEN DOOR SYSTEMS INTERNATIONAL LIMITED | 22/11/16 |
|
2 | NREA0101021491 | ELECTRIFICATION OF GAIDAR FULANI, KANO STATE | 33,384,318.48 | A & Y EDUCATIONAL CONECT LIMITED | 22/11/16 |
|
3 | NREA0101021358 | RURAL ELECTRIFICAION IN ALBASU/AJINGI, KANO STATE | 77,101,552.20 | RAFJAF NIGERIA LTD. | 22/11/16 |
|
4 | NREA0101121206 | SUPPLY OF TRANSFORMERS TO DALA FED CONST KANO STATE | NIL |
|
||
5 | NREA0101021481 | INSTALLATION OF 1x7.5MVA, 33/11KV AND 11KV PANEL IN INJECTION SUBSTATION AT FAGE, KANO STATE | BESTCO NIG. LTD |
|
||
6 | NREA0101021482 | ELECTRIFICATION OF KATAMI/SANI MUAZU DANKUMBO, KANO STATE | 60,343,355.00 | AL-AMSAN INT'L LTD | 27/02/06 |
|
S/N | BUDGET CODE | PROJECTS | TOTAL COST | NAME OF CONTRACTOR | PROJECT COMMENCEMENT DATE | |
1 | NREA0101021490 | ELECTRIFICATION OF JAMA'A FAGON FULANI, KATSINA STATE | 28,640,551.10 | RASTAG GLOBAL SERVICES LIMITED | 22/11/16 |
|
2 | NREA0101020956 | COMPLETION OF 10 NO. ON-GOING ELECTRIFICATION PROJECTS IN KATSINA STATE | Refer to status of ongoing |
|
||
3 | Zonal Intervention | RURAL ELECTRIFICATION AT DANDUME LGA, FUNTUA/DANDUME, KATSINA STATE | LIBERTY OVERSEES BROTHERS LTD |
S/N | BUDGET CODE | PROJECTS | TOTAL COST | NAME OF CONTRACTOR | PROJECT COMMENCEMENT DATE | |
1 | NREA0101021479 | ELECTRIFICATION OF UNGUWAR ABUJA & DUNARI TOWN IN MALAM MADORI LGA, JIGAWA STATE |
52,799,712.00 | SHANEC NIG. LTD | 18/01/07 |
|
2 | NREA0101021480 | ELECTRIFICATION OF YALWA (MALARI) TOGORO & MAKADDAKI, JIGAWA STATE | 68,134,278.00 | DAMSAL NIG. LTD | 27/02/06 |
|
3 | NREA0101021489 | CONSTRUCTION OF 7.5 MVA AT BKUDU, JIGAWA STATE | NABEELAH |
|
||
4 | NREA0101020953 | COMPLETION OF ON-GOING ELECTRIFICATION PROJECTS IN JIGAWA STATE | Refer to status of ongoing |
|
S/N | BUDGET CODE | PROJECTS | TOTAL COST | NAME OF CONTRACTOR | PROJECT COMMENCEMENT DATE | |
1 | NREA0101020957 | COMPLETION OF 3 NO.ON-GOING ELECTRIFICATION PROJECTS IN KEBBI STATE | Refer to status of ongoing |
|
S/N | BUDGET CODE | PROJECTS | TOTAL COST | NAME OF CONTRACTOR | PROJECT COMMENCEMENT DATE | |
1 | NREA0101020957 | COMPLETION OF 3 NO.ON-GOING ELECTRIFICATION PROJECTS IN KEBBI STATE | Refer to status of ongoing |
|
S/N | BUDGET CODE | PROJECTS | TOTAL COST | NAME OF CONTRACTOR | PROJECT COMMENCEMENT DATE | |
1 | NREA0101021017 | COMPLETION OF 4 NO. ON-GOING ELECTRIFICATION PROJECTS IN ZAMFARA STATE | Refer to status of ongoing |
|